Progress of Cuban Mining Project Highlighted |
|
|
Monday, March 19, 2018
Havana.- The Castellanos mining project, in the western province of Pinar del Rio, exported 24,000 tons of lead and zinc from December to February.
Experts from the sector pointed out that during the said period, some 7,000 tons of concentrated lead and 17,000 tons of zinc were exported.
The investment totaled around 270 million dollars to activate Castellanos deposit, which has reserves for 11 years of exploitation.
In addition, the Santa Lucía deposit will allow extending the useful life of the plant for another 14 years.
In the preparation of the project, some three million cubic meters of sterile materials were removed to reach the ore.
|
|
|
|
|
|
|
|